Commissioning

Media

SIGMA has a good experience for installation and commissioning of industrial automation system. In this regard sigma well done following activities in the projects:

EQUIPMENT CHECKOUT

Equipment Checkout includes verification that the equipment is fully connected electrically and mechanically and that it can be operated by the control system. Representatives of the electrical contractor, mechanical contractor (if applicable) and a representative of the owner should be present to verify proper operation of the equipment. Equipment checkout tasks include:

  • Motor rotation checks
  • Valve operation
  • Control device operation
SYSTEM COMMISSIONING

System Commissioning includes verification that start-up sequences, interlocking, and shut down sequences are working correctly. Systems will also be dry run and flushed of any foreign materials. Representatives of the electrical contractor, mechanical contractor (if applicable) and a representative of the owner should be present to verify proper operation of the equipment.

PROCESS STARTUP

Process startup begins once all equipment has been checked out and commissioned. This includes assisting plant operators in initial production, monitoring the control system operation, fine-tuning operations, monitoring alarm conditions, verifying data collection, and recording changes to allow for accurate documentation. 
SIGMA recommends that the owner be responsible for scheduling and coordinating the process startup portion of the project.